Viktor Vesnin and Nikolai Kolli designed the buildings of this power station on the Dnieper River at Zaporizhzhia. It was a central project of the Soviet electrification plan. Construction began in 1927 and the first power flowed in October 1932.
The dam is 197 feet (60 meters) high and 2,493 feet (760 meters) long and raises the river by 37.5 meters, forming a reservoir that stretches 129 kilometers upstream. The station's installed capacity is 1,578.6 megawatts, counting the second powerhouse added between 1969 and 1980.
Retreating Soviet troops blew up the dam in 1941 to slow the German advance. The flood that followed killed thousands, with estimates varying widely. The station was rebuilt between 1944 and 1950. Russian missile strikes in March 2024 damaged it and stopped power output. A highway runs along the dam.