The 25 de Abril Bridge carries traffic across the Tagus River between Lisbon and Almada. It opened on August 6, 1966, as the Ponte Salazar, named for the dictator who ordered it. Steinman, Boynton, Gronquist and London of New York designed it with Tudor Engineering, and the American Bridge Company built it.
The suspension bridge is 10,410 feet (3,173 meters) long, with a main span of 3,323 feet (1,012.9 meters). Each tower stands 625 feet (190.5 meters) tall. Six road lanes run on the upper deck. The lower deck was planned from the start but dropped to save money, and a double-track electric railway finally opened there on June 30, 1999.
The bridge took its present name after the Carnation Revolution of April 25, 1974. Pedestrians cannot normally cross it, except during an annual half-marathon. An observation deck opened in September 2017 and lets visitors go out onto the structure.